Ram can complete a project in 15 days, and Shyam can complete the same project in 20 days. If they work together, how long will it take them to finish the project?
MCQ Subject: Time & Work
-
If 12 workers complete a job in 10 days, how many days…
If 12 workers complete a job in 10 days, how many days for 15 workers to do the same job?
-
Four workers, P, Q, R, and S, can complete a job in…
Four workers, P, Q, R, and S, can complete a job in 5, 10, 15, and 20 days respectively. How many days will it take for all four to complete the job together?
-
If 12 workers complete a project in 10 days, how many days…
If 12 workers complete a project in 10 days, how many days would 8 workers take at the same efficiency?
-
If 15 workers can finish a project in 24 days, how many…
If 15 workers can finish a project in 24 days, how many days would it take for 10 workers to complete the same project, assuming the work rate remains constant?
-
A can finish a work in 10 days, B in 15 days.…
A can finish a work in 10 days, B in 15 days. If A works for 4 days, how many more days does B need to complete the work?
-
If 15 workers can build a wall in 24 days, how many…
If 15 workers can build a wall in 24 days, how many workers are needed to build the same wall in 10 days?
-
If 5 workers can complete a job in 24 days, how many…
If 5 workers can complete a job in 24 days, how many days would 8 workers take to complete the same job, assuming the work rate is constant?
-
If 15 workers can complete a project in 48 days, how many…
If 15 workers can complete a project in 48 days, how many days would it take for 24 workers to complete the same project, assuming the work efficiency remains constant?
-
If 12 workers complete a project in 20 days, how many days…
If 12 workers complete a project in 20 days, how many days will it take for 8 workers to complete the same project, assuming the work rate remains constant?